Customs Moves to Clear Over 300 Long-Stranded Power Equipment Containers

Spread the love

The Nigeria Customs Service (NCS) has commenced the clearance of more than 300 containers of electricity transmission equipment that have remained stranded at Nigerian seaports for between 14 and 20 years, following directives from the Federal Government aimed at unlocking critical infrastructure assets for the nation’s power sector.

The clearance exercise follows an intervention by the Federal Ministry of Finance, which directed the Customs Service to expedite the release of the consignments, citing their importance to Nigeria’s electricity transmission network and ongoing power sector reforms.

Confirming the development, the National Public Relations Officer of the NCS, Deputy Comptroller Abdullahi Maiwada, disclosed that the Service had received an official communication from the Ministry of Finance authorizing the accelerated release of the equipment.

According to him, the directive was personally signed by the Minister of Finance and Coordinating Minister of the Economy, underscoring the urgency attached to the matter by the Federal Government.

“The Nigeria Customs Service has received a directive from the Ministry of Finance, duly signed by the Honourable Minister of Finance and Coordinating Minister of the Economy, instructing the Service to expedite the release of the power equipment,” Maiwada stated.

The initiative also aligns with President Bola Ahmed Tinubu’s directive for the immediate clearance of the containers after the issue was brought before the Federal Executive Council (FEC) by the Minister of Power, Chief Adebayo Adelabu.

The containers reportedly contain essential transmission infrastructure, including high-capacity transformers, power cables, switchgear, and other specialized electrical equipment imported by the Federal Government through the Ministry of Power and the Transmission Company of Nigeria (TCN) for strategic electricity projects.

The equipment is intended for deployment across several flagship projects, including the National Integrated Power Project (NIPP), donor-funded transmission initiatives, and the Presidential Power Initiative (PPI).

Government officials attributed the prolonged delay in releasing the consignments to a combination of outstanding port charges, incomplete customs documentation, and administrative bottlenecks involving multiple government agencies.

Some of the equipment, despite being procured for vital electricity infrastructure projects, has remained at the ports for nearly two decades, limiting its contribution to national efforts aimed at improving power supply and transmission efficiency.

Much of the equipment was sourced from international manufacturers in countries such as China and Germany, owing to the advanced technology required for the production of high-capacity transformers and related transmission systems that are currently not manufactured locally.

To facilitate the release process, President Tinubu has directed the Ministry of Power to work closely with the Nigerian Ports Authority (NPA) and the Nigeria Customs Service to resolve all outstanding financial obligations and administrative challenges delaying the clearance of the consignments.

Following their release, technical experts will conduct comprehensive inspections to determine the operational status of the equipment. Components deemed serviceable will be integrated into ongoing electricity projects, while obsolete or damaged items will be appropriately disposed of.

The equipment is expected to play a pivotal role in strengthening Nigeria’s transmission network and supporting grid stabilization efforts, particularly under the proposed East and West Super Grid projects, which aim to expand the country’s electricity transmission capacity from approximately 5,000MW to 19,000MW.

The planned expansion also encompasses critical transmission corridors, including the Lagos-Enugu-Port Harcourt and Abuja-Kaduna-Kano routes, as well as the upgrade and construction of substations across the country.

Industry stakeholders say the commencement of the clearance process highlights the substantial economic costs associated with prolonged cargo delays at Nigerian ports, including mounting demurrage fees, storage charges, and project implementation setbacks.

While the clearance exercise has officially begun, authorities have yet to announce a definitive timeline for the complete release, inspection, and deployment of all affected equipment.

Significance of the Exercise
The release of the long-detained power equipment represents a major step toward enhancing Nigeria’s electricity infrastructure. Beyond recovering valuable national assets, the initiative is expected to accelerate key transmission projects, improve grid reliability, support economic growth, and advance the Federal Government’s broader objective of delivering a more stable and efficient power supply to millions of Nigerians.